Dear Sirs,
I would like to ask regarding the Dialux 4.13 calculation report the option to eliminate the date at the header of the report.
The same applies for:
Operator
Telephone
Fax
e-Mail

Regards,
Charalambos

Re: Dialux 4.13 calculation report format

Posted: Mon Jan 13, 2020 8:03 am
by Csuleiman
Dear Charalambos,

Either delete this information directly in the project manager in the tab "Contact" or via the menu "File -> Settings -> General options -> Contact". Please see screenshots below.

Screenshot 1_.JPG
Screenshot 1_.JPG (117.99 KiB) Viewed 1574 times
Screenshot 2_.JPG
Screenshot 2_.JPG (125.2 KiB) Viewed 1574 times

Unfortunately, it is not possible to delete the date nor the operator.

Best regards,